Aqua Patch repair sequence

Stage 01

Pour Aqua Patch

Empty the bag directly into the pothole. The bag is ready to use — no mixing or heating.

Stage 02

Sweep flat

Sweep or rake the product level across the hole, leaving a shallow allowance above the surface for compaction.

Stage 03

Pour water

Pour at least 1 L of water per 20 kg bag; 2 L is a safe field rate. Excess water is acceptable.

Stage 04

Stamp flat

Compact immediately after watering. Drive over the repair straight away; it is hard as a rock an hour later. Allow about 2 hours at intersections and turning areas.

Scroll to advance

Cross-section of an Aqua Patch pothole repair, shown in four stages An Aqua Patch bag is turned upside down and black aggregate is poured into a water-filled pothole. The product is swept flat, watered at 2 L per 20 kg bag and stamped flat. A heavy semi-trailer rolls over the repair immediately after compaction; the repair hardens within the hour. Repair Asphalt/Concrete AQUA PATCH Ready to use SWEEP FLAT 2 L PER BAG STAMP FLAT TRAFFICABLE NOW AQUA PATCH WATER-ACTIVATED REPAIR
Skip animation

Aqua Patch repair sequence

Four stages, one simple repair.

  1. Stage 01

    Pour Aqua Patch

    Empty the bag directly into the pothole. The bag is ready to use — no mixing or heating.

  2. Stage 02

    Sweep flat

    Sweep or rake the product level across the hole, leaving a shallow allowance above the surface for compaction.

  3. Stage 03

    Pour water

    Pour at least 1 L of water per 20 kg bag; 2 L is a safe field rate. Excess water is acceptable.

  4. Stage 04

    Stamp flat

    Compact immediately after watering. Drive over the repair straight away; it is hard as a rock an hour later. Allow about 2 hours at intersections and turning areas.

What is Aqua Patch?

A cold-mix repair product activated by water.

Aqua Patch is a high-performance, water-activated cold-mix repair product for asphalt and concrete surfaces. It is supplied ready to use in 20 kg bags — no mixing, heating or special plant required.

Made in Japan, Aqua Patch combines a graded hard-stone aggregate with a proprietary plant-based binder. It contains no petroleum-based solvents. Water triggers the chemical reaction that hardens the mix, rather than waiting for a solvent to evaporate.

Aggregate
A precise blend of quality crushed hard stone (such as limestone or granite) and sand. 5 mm and 13 mm nominal mixes, February 2026 technical data.
Binder
A proprietary, plant-based organic binder. It contains no petroleum-based solvents and hardens through a chemical reaction with water. Approximately 50% of the asphalt binder is replaced with bio-based material.
Suited for all Australian conditions
Made in Japan using sustainable practices, Holds tough in all Australian conditions from extreme heat to torrential rain.
Packaging
60 × 20 kg bags per 1.2 t pallet; pallet dimensions 1,100 × 1,100 × 800 mm. Do not stack pallets; maximum 10 bags high when storing loose bags.
Aqua Patch bag beside a pile of the aggregate product at the edge of a pothole
Aqua Patch ready to use at a pothole repair

Activation

Water

Format

20 kg bag

Strengths

Built around wet-weather repair and fast reinstatement.

A permanent, water-activated patch that can be opened to traffic immediately and reaches hot-mix-like strength without heating or solvents.

  • Water-activated and weatherproof

    Install in the rain, or pour directly into a water-filled pothole. No pumping required.

  • Traffic-ready immediately

    Drive over it straight after watering and compaction. Hard as a rock an hour later. Allow about 2 hours at intersections and turning areas.

  • Durable, permanent repair

    Independent testing shows 5.0 kN Marshall stability and 1,900 MPa resilient modulus after 7 days. Wheel-track rut just 1.5 mm after 24 hours conditioning.

  • Non-toxic, low-impact binder

    A bio-based binder replaces around 50% of the asphalt binder. No petroleum-based distillate solvents; no hydrocarbon leaching or evaporation per the SDS.

Comparisons

How it differs from conventional repair methods.

Generic category comparisons, based on the product format and manufacturer information. Individual site conditions and methods vary.

Aqua Patch vs traditional cold-mix asphalt

Traditional cold-mix asphalt

Relies on solvent evaporation to cure, stays soft for months, tracks onto tyres and is often pushed out of the hole, leading to repeat repairs.

Aqua Patch

Water-activated chemical reaction; cures solid with no sticky residue.

Aqua Patch vs hot-mix asphalt

Hot-mix asphalt

Needs heating, heavy plant, specialised crews and complex logistics; must be placed before it cools.

Aqua Patch

Ready to use in a bag; no heat or heavy plant; one person with a shovel, water and a tamper can apply it.

-

Use cases

Small-batch repairs, reactive maintenance and reinstatement.

Aqua Patch is suited to localised pavement defects and reinstatement work where a fast, contained repair is needed.

01Technical situations

  • Pothole and rut repairs

    Localised surface defects in asphalt pavements, including water-filled potholes.

  • Utility cuts and trench reinstatements

    Small reinstatement areas around service trenches and utility openings.

  • Manhole and service cover levelling

    Edge repairs and localised levelling around covers and frames.

  • Driveway and pavement trip-hazard levelling

    Shallow surface defects and uneven transitions in pedestrian and vehicle areas.

  • Water-filled pavement craters

    Repairs where standing water is present and pumping is impractical.

02Locations

  • Highways and arterial roads

    Subject to road authority approval, TTM requirements and site-specific specifications.

  • Local council streets

    Reactive patching and small-batch maintenance across urban and regional networks.

  • Commercial car parks and industrial loading docks

    Localised repairs where fast reinstatement matters and heavy plant access is limited.

  • Residential driveways and body corporate roads

    Small, contained repairs using basic hand tools.

  • School grounds and public parks

    Repair of localised surface hazards in controlled-access areas.

Worker pouring Aqua Patch from the bag into a pothole
Aqua Patch poured directly into a pothole

How to use it

No mixing. No heating. No special tools.

Five steps, one person and a standard hand tamper. The method is deliberately simple; site-specific requirements still apply.

Tools required

A shovel or rake, water, and a hand tamper. That is the basic kit.

  1. 01

    Clean

    Sweep out loose debris, dirt and large rocks. Standing water does not need removing.

  2. 02

    Pour Aqua Patch

    Empty the bag into the hole. For holes deeper than 50 mm, place and compact in layers.

  3. 03

    Sweep flat

    Sweep or rake the product level, leaving about 30% above the surrounding surface for compaction — roughly 15 mm on a 50 mm repair.

  4. 04

    Pour water

    Pour water evenly over the patch — at least 1 L per 20 kg bag. 2 L is a safe field rate, and excess water is acceptable.

  5. 05

    Stamp flat

    Compact immediately after watering. Drive over the repair straight away; it is hard as a rock an hour later. Allow about 2 hours at intersections and turning areas.

Site safety

Follow your road authority’s TTM requirements and WHS procedures, wear appropriate PPE, and read the Safety Data Sheet (SDS).

Safety Data Sheet and technical documents

Watch the method

A 2.5-minute guide to the product and application method.

Click to load · no autoplay

Quantity calculator

Estimate bags, water and pallets.

Enter the repair dimensions to estimate the Aqua Patch required. The calculation includes the 15 mm compaction mound and your waste allowance.

Included in the estimate

  • 15 mm compaction mound
  • Your waste / safety allowance
  • Water quantity and layer guidance
1. Repair shape

Depth is always entered in millimetres. Irregular repairs use an approximate area in m².

m
m
mm

Minimum repair depth: 20 mm for the 5 mm mix; 30 mm for the 13 mm mix.

%

No data is sent. Calculation runs in your browser.

Estimated requirement

Enter the repair dimensions and select Calculate quantities to see an estimate.

Estimates only. Confirm quantities for your site conditions.

Compacted density: 2,300 kg/m³ (manufacturer coverage data). 60 bags per 1.2 t pallet.

Client experience

Experiences from the field.

Testimonials are published only after permission and verification. Approved client experiences will appear here.

Client experiences are being verified. [PLACEHOLDER]: approved testimonials pending permission

Testimonials added in the CMS are published only when approved is true and verification is recorded. The two placeholder quotes in the CMS remain unverified.

Client feedback

Share your Aqua Patch experience

We publish experiences only with permission and after verification. Submissions are reviewed before anything is made public.

Do not include confidential or commercially sensitive information.

Submissions are reviewed before publication. See the privacy policy.

How to buy

Talk to us about a trial, a pallet or a programme of works.

Aqua Patch is supplied in 20 kg bags and 60-bag pallets (1.2 t). Pay for pallets online by card, or contact us for project quantities, freight and account terms.

Wholesale and bulk enquiry

For councils, contractors, distributors and property managers. Fields marked * are required.

Submissions are processed by Netlify Forms. You will be taken to a confirmation page.

Direct contact

Direct contact

Prefer to speak to someone? Contact Y Block Pty Ltd directly.

Y Block Pty Ltd · Dante Cremasco, Principal

Head office
29 Robinson St
Brighton East VIC 3187
Australia
Hours
Contact us to arrange a time.
Entity
Y Block Pty Ltd · ACN 626 968 401
ATF Air Cooled Trust
Y Block Pty Ltd

Pay for a pallet

Buy 13 mm pallets online by card. Each pallet contains 60 bags. Card details are entered on eWAY’s secure hosted page; freight is quoted separately.

Pay by card

Procurement support

Bulk pallet orders, freight, trials, supplier registration and WHS documentation. Contact us for project quantities and account terms.

Procurement details for councils and contractors

Where to buy

Where to buy

Search the authorised stockist list by state or postcode. Select a location to show it on the map.

Search runs in your browser. The map is an embedded Google Maps preview.

1 stockists listed

Distributor Head office

Aqua Patch Australia Office

VIC

29 Robinson St, Brighton East VIC 3187

+61 419 105 316

Stockist map

The head office is shown by default. Select another location from the list to show it on Google Maps.

Showing: Aqua Patch Australia Office

About

Local supply, backed by a global manufacturer.

Supplied in Australia and New Zealand by Y Block Pty Ltd

Y Block Pty Ltd is the Australian and New Zealand supplier of Aqua Patch. Our mission is to bring a faster, greener, permanent infrastructure maintenance solution to councils, contractors and residents across both countries.

Local support and dispatch from the Epping, Victoria warehouse, with Caboolture, Queensland stock available on request. Y Block Pty Ltd · ABN 23 757 080 744 · ACN 626 968 401 · ATF Air Cooled Trust.

Aqua Patch manufacturing and product operations in Japan
Manufacturing and product operations, Japan

Manufacturing partner

Manufactured by Maeda Road Construction

Aqua Patch is manufactured in Tokyo by Maeda Road Construction Co., Ltd., one of Japan’s largest asphalt producers. JALUX Inc. is the international distributor. Y Block Pty Ltd holds the exclusive importation and distribution rights for Australia and New Zealand.

Manufacturer
Maeda Road Construction
Headquarters
Tokyo, Japan
International distribution
JALUX Inc.

Behind the scenes

From manufacture in Japan to arrival at distribution hubs in Australia and New Zealand.

FAQ

Common questions.

Common questions answered from the current technical documents. Contact us for project-specific advice.

View all frequently asked questions
Can it be used in the rain?

Yes. Aqua Patch is water-activated and can be applied in wet conditions or directly into a water-filled pothole. Excess water is acceptable; standing water does not need to be pumped out.

How soon can I drive over the repair?

Straight-line traffic can drive over the repair immediately after watering and compaction. It is hard as a rock an hour later. Allow about 2 hours at intersections and in areas where wheels turn on the patch.

How much water does it need?

Use at least 1 L of water per 20 kg bag. Around 1.5 L is typical, and 2 L is a safe field rate. Excess water will not damage the repair. The site calculator uses 2 L per bag as a conservative allowance.

What is the shelf life?

Unopened bags have a 12-month shelf life from the manufacturing date. Once opened, use the bag promptly and seal any remainder tightly; moisture in the air will begin the curing reaction.